The works will be performed in seven sections: Daugavgrīva, Mangaļi, Mangaļsala, Vecmīlgrāvis, Jaunmīlgrāvis, and near Krievu Island.
The planned performance: from May to the end of July 2021.
We kindly ask the owners of recreational vessels to observe precautions during the works.